Construction Updates

Week of May 13-17
Herrero Builders    Monday  Tuesday  Wednesday  Thursday  Friday
    Remove   store fronts   x x      
    Frame   up barrier at store front     x x x  
    Misc.   demo   x x x x x
    Clean   up   x x x x x
    Lay   out walls for trades     x x x  
    Start   rough in of overhead electric   x x x x  
    Work   exterior clock conduits & set line       x x  
    Start overhead Plumbing   x x x x x
    splice in overhead duct work   x x x x x
    trouble   shoot & lay in thermo wire overhead       x x x
    Saw cut &   demo concrete for footing & wall   x x      
    saw cut trenchs electric &   plumbing x   x x    
    remove concrete   & dig trench's     x x x x
                 

 

Turf Carpet installation                           Noise                   All Week

Emilie Avenue Swale Irrigation/Planting                Minor Traffic Impact                    All Week

Fencing Safety Netting/misc                                         Minor noise                        All week

East Landscape Utilities/irrigation                                   Noise                               All week